Allegations of widespread irregularities and poor construction quality have emerged over a Tk 15 million (1.5 crore) infrastructure project at Satchari National Park in Habiganj, one of the most popular tourist destinations in Bangladesh's Sylhet Division.
Even before the project was officially inaugurated, sections of the bridge approach road and guide wall collapsed, triggering criticism from tourists and local residents.
Locals alleged that the damage resulted from the use of substandard construction materials and a lack of proper supervision during the project. A visitor, identified as Sentu, said the absence of regular monitoring had led to serious irregularities, describing the situation as "very disappointing."
Attempts to obtain comments from the contractor responsible for the project were unsuccessful.
Shafiqul Islam Abul, President of the Satchari National Park Co-management Committee, said it was unfortunate that the bridge had suffered damage before its inauguration and expressed hope that the authorities would take appropriate action.
Chunarughat Upazila Engineer Fazlul Haque said heavy rainfall and strong currents from the nearby hill stream had caused parts of the approach road and guide wall to collapse. However, he also acknowledged negligence on the part of the contractor and assured that the damage would be repaired promptly.
Chunarughat Upazila Nirbahi Officer (UNO) Galib Chowdhury said he had already inspected the damaged site. He added that a team of specialists from Dhaka would assess the situation, after which the damaged sections would be reconstructed based on their recommendations. He also said action would be taken if evidence of construction irregularities is found.
According to project information, the Local Government Engineering Department (LGED) began construction of the bridge in May 2023 at a cost of nearly Tk 15 million to improve visitor access to Satchari National Park.
The project was scheduled for completion by December 2025, but despite missing the deadline, the work remains unfinished. Around 70% of the project payment has already been released.
A visit to the site revealed that both ends of the bridge's approach road had collapsed, while large sections of the guide wall had been severely damaged. Several concrete blocks had shifted from their original positions, geotextile layers were torn, and scattered blocks were visible inside the stream.
Local residents claimed the contractor carried out poor-quality work due to inadequate supervision. Authorities are currently using around 200 bags of sand as a temporary measure to allow visitors to cross the damaged section while emergency repair work continues.
Resident Abdul Zahir Mia called for a thorough investigation and legal action against those responsible, saying such irregularities at one of the country's leading tourist attractions are unacceptable.