Rainwater is leaking through the roof of the Jatiya Sangsad Bhaban whenever it rains, raising concerns about the condition of the iconic parliament complex. Similar problems have also been reported at the South Plaza, VIP bungalows, ministerial hostels, former MPs’ hostel and secretariat hostel within the complex.
Due to years of inadequate maintenance, rainwater leaking through the roof is threatening equipment worth around Tk 2,000 crore at the Main Mechanical Plant (MMP). Temporary tin shelters have been installed over the equipment to protect them from water. However, the situation has created a serious risk of short circuits that could potentially disrupt the electrical system of the entire complex.
Waterlogging is another problem. Among the entrances to the Parliament Building, the Bakultala Gate on Manik Mia Avenue becomes flooded even after light rainfall.
During a visit to the site, it was found that the Main Mechanical Plant is located beneath the South Plaza. The facility houses the Parliament Building’s central air-conditioning system, GIS panels, six generators, an electrical substation and a central store room.
Whenever it rains, water leaks through the roof and floods the MMP room, where equipment worth around Tk 2,000 crore is installed. Since water conducts electricity, the leaking water poses a significant risk of short circuits and potentially serious accidents.
As a temporary measure, tin shelters have been installed above the equipment under the South Plaza roof. Efforts are also underway to repair the joints of the glass bricks to prevent water from entering the Parliament Building. Roofs of several buildings are also being made water-resistant.
Experts, however, have questioned the effectiveness of these temporary measures, saying that various forms of mismanagement and inadequate maintenance have left the National Parliament Building, designed by renowned architect Louis I. Kahn, in a vulnerable condition.
Chief Whip of the National Parliament Nurul Islam Moni told a local media outlet that a project is being prepared to identify all problems in the Parliament Building and carry out the necessary renovations. Work has already begun, he said.
The issue was first raised in Parliament during the recently concluded budget session by government whip G K Gaus. Drawing the Speaker’s attention to the matter, he said buckets had been placed in rows in front of the mosque because rainwater continuously leaked through the roof.
He pointed out that Parliament had just approved a massive budget of Tk 9.38 lakh crore and said such a deplorable condition inside the complex, including the mosque, was unacceptable.
Deputy Speaker Barrister Kaiser Kamal, who was presiding over the session at the time, said they were also aware of rainwater leaking through the Parliament roof. He added that he himself had to keep a bucket near the ceiling when sleeping in his own room.
Chief Whip Nurul Islam Moni said the issue falls under the jurisdiction of the Ministry of Housing and Public Works and that immediate steps would be taken to resolve it.
The Deputy Speaker then drew the attention of Housing and Public Works Minister Zakaria Taher, who was present in Parliament. The minister said all-out measures were being taken to resolve the problem and that a solution would be found soon.
According to reports, the ministry has already started repair work at locations in the Parliament Building where rainwater is leaking. However, the work is progressing slowly, which has also sparked dissatisfaction.